| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AG18BB | Estudio en zona urbana de uso del suelo. | km/vÃa |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Mano de Obra | |||||
| T19 | Ingeniero "H" | Turno | 0.050000 | $848.65 | $42.43 |
| T17 | Ingeniero "F" | Turno | 0.100000 | $607.33 | $60.73 |
| T15 | Ingeniero "D" | Turno | 0.500000 | $461.64 | $230.82 |
| T05 | Pasante de ingeniero | Turno | 0.500000 | $261.88 | $130.94 |
| T19 | Ingeniero "H" | Turno | 0.050000 | $848.65 | $42.43 |
| T17 | Ingeniero "F" | Turno | 0.100000 | $607.33 | $60.73 |
| T15 | Ingeniero "D" | Turno | 0.500000 | $461.64 | $230.82 |
| T05 | Pasante de ingeniero | Turno | 0.500000 | $261.88 | $130.94 |
| S12 | Dibujante "C" | Turno | 0.100000 | $212.11 | $21.21 |
| T19 | Ingeniero "H" | Turno | 0.025000 | $848.65 | $21.22 |
| T17 | Ingeniero "F" | Turno | 0.050000 | $607.33 | $30.37 |
| T07 | Ingeniero "B" | Turno | 0.250000 | $328.06 | $82.02 |
| B13 | Ayudante de topógrafo | Turno | 1.000000 | $94.09 | $94.09 |
| T19 | Ingeniero "H" | Turno | 0.025000 | $848.65 | $21.22 |
| T17 | Ingeniero "F" | Turno | 0.050000 | $607.33 | $30.37 |
| T07 | Ingeniero "B" | Turno | 0.250000 | $328.06 | $82.02 |
| S12 | Dibujante "C" | Turno | 1.000000 | $212.11 | $212.11 |
| Suma de Mano de Obra | $1,524.47 | ||||
| Herramienta | |||||
| 09 | Herramienta menor. | (%)mo | 0.030000 | $1,524.47 | $45.73 |
| Suma de Herramienta | $45.73 | ||||
| Equipo | |||||
| V6FG | Camioneta Pick-up con operación.Marca: Ford Modelo: F-150 | Hora | 4.000000 | $133.01 | $532.04 |
| V6FG | Camioneta Pick-up con operación.Marca: Ford Modelo: F-150 | Hora | 2.000000 | $133.01 | $266.02 |
| Suma de Equipo | $798.06 | ||||
| Costo Directo | $2,368.26 |