| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | | | | |
| ADITIVO-ASF | Aditivo para mezcla asfaltica | lts | 0.600000 | $35.00 | $21.00 |
| PRUEBA MARSHALL | Prueba marshall | prue | 0.000050 | $45,000.00 | $2.25 |
| Suma de Material | | | | $23.25 |
| Herramienta | | | | |
| HERRAMIENTA | HERRAMIENTA MENOR | (%)mo | 1.000000 | $0.00 | $0.00 |
| Suma de Herramienta | | | | $0.00 |
| Equipo | | | | |
| EQPIPA | PIPA DE AGUA DOGDE DE 6,000 LTS 125 HP | hora | 0.003000 | $168.64 | $0.51 |
| EQ50 | MOTOCONFORMADORA CATERPILLAR 12 F 130 HP | hora | 0.015000 | $442.50 | $6.64 |
| EQ33 | COMPACTADOR DE RODILLO LISO DE 145 HP CON CONTROLES QUE MODIFIQUE LA AMPLITUD Y FRECUENCIA DE VIBRACION | hora | 0.010000 | $427.70 | $4.28 |
| EQ0027 | TANQUE DE ALMACENAMIENTI TIPO PETROLERO, SATEÑA CAP. 40,000 LTS CON QUEMADORES | hora | 0.024000 | $105.10 | $2.52 |
| EQADM | PLANTA DE MEZCLA EN CALIENTE MARCA ADM DE 110 TN/HR, INCLUYE: PLANTA ALIMENTADORA DE LUZ, Y COSTO DE INSTALACION DE LA MISMA, 215 HP | hora | 0.162000 | $2,534.02 | $410.51 |
| EQ0FINIS | EXTENDEDORA FINISHER MCA. BLAW-NOX F-180H DE 180 HP | hora | 0.080000 | $655.64 | $52.45 |
| EQ0003 | COMPACTADOR DE RODILLO LISO DYNAPAC CA301d DE 135 HP DE 2.13 m TAMBOR Y PESO DE 14 TN | hora | 0.045000 | $451.53 | $20.32 |
| EQ0008 | COMPACTADOR SOBRE NEUMATICOS MCA. DYNAPAC CP221 DE 100HP ANCHO DE RODADO 1.83 M | hora | 0.045000 | $351.94 | $15.84 |
| EQ00008 | CARGADOR FRONTAL 966-C DE 190 HP | hora | 0.140000 | $528.67 | $74.01 |
| EQ0027 | TANQUE DE ALMACENAMIENTI TIPO PETROLERO, SATEÑA CAP. 40,000 LTS CON QUEMADORES | hora | 0.008000 | $105.10 | $0.84 |
| EQ0006 | PETROLIZADORA MCA. ESCUDERO DE 6000 LTS DE BOMBA 756 IPM BARRA de 3.6 m ,SOBRE CAMION MCA DODGE DE 155 HP | hora | 0.004000 | $263.36 | $1.05 |
| EQBAR | BARREDORA ROTATORIA AUTOPROPULSADA 90 HP CON FILAMENTO MODELO V35 MARCA CATERPILLAR | hora | 0.008000 | $275.51 | $2.20 |
| Suma de Equipo | | | | $591.17 |
| Auxiliar | | | | |
| ACAR1 | ACARREO EN CAMION DE VOLTEO DEL 1er KM SOBRE TERRACERIAS | M3 | 1.000000 | $7.54 | $7.54 |
| ACAR5 | ACARREO EN KM SUBSECUENTE DEL KM 2 AL 20 | m3 | 18.000000 | $3.69 | $66.42 |
| BASAGUA | AGUA | M3 | 0.100000 | $14.30 | $1.43 |
| ACAR1 | ACARREO EN CAMION DE VOLTEO DEL 1er KM SOBRE TERRACERIAS | M3 | 1.200000 | $7.54 | $9.05 |
| ACAR5 | ACARREO EN KM SUBSECUENTE DEL KM 2 AL 20 | m3 | 2.400000 | $3.69 | $8.86 |
| CUA1 | CUADRILLA 1/20 CABO + 4 CINCO OBREROS | JOR | 0.008000 | $897.51 | $7.18 |
| BASMAT3/4 | SUMINISTRO Y EXTRACCION DE MATERIAL PETREO PARA BASE Y SUB BASE DE 3/4" A FINOS | M3 | 1.000000 | $50.05 | $50.05 |
| CUADRILLA LIMPIEZA | CUADRILLA DE LIMPIEZA Y CONSERVACION DE CARRETERA | JR | 0.000150 | $1,715.07 | $0.26 |
| MATERIAL CARPETA | Auxiliar de produccion de material petreo para mezcla asfaltica modificada | M3 | 1.000000 | $174.09 | $174.09 |
| Suma de Auxiliar | | | | $324.87 |
| Costo Directo | | | | $939.29 |