| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-94 | SUMINISTRO E INSTALACION DE LAMINA ANTIDERRAPANTE DE 0.94 M DE ANCHO DE 3/16" DE ESPESOR INCLUYE HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PLACA DE ACERO 1/4"1 | PLACA DE ACERO DE 1/4" | KG | 15.262000 | $12.50 | $190.78 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 1.300000 | $49.88 | $64.84 |
| ACETILENO 1 | ACETILENO | KG | 0.480000 | $130.00 | $62.40 |
| OXIGENO 1 | OXIGENO | M3 | 0.360000 | $39.00 | $14.04 |
| BARRENAN 3/8"X42 1 | BARRENANCLA DE 3/8" x 4" | PZA | 4.000000 | $7.00 | $28.00 |
| ADITIVO ANTIRUST 1 | ADITIVO PARA FRENAR CORROSION ANTIRUST | LTO | 0.700000 | $80.00 | $56.00 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.400000 | $90.00 | $36.00 |
| BISAGRA P/REJ 1 | BISAGRA TUBULAR CON PASADOR DE 3/8" | PZA | 2.000000 | $48.00 | $96.00 |
| Suma de Material | $548.06 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.040000 | $290.45 | $11.62 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.400000 | $233.90 | $93.56 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.400000 | $181.41 | $72.56 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.400000 | $169.01 | $67.60 |
| Suma de Mano de Obra | $245.35 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 0.250000 | $111.52 | $27.88 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 0.250000 | $24.34 | $6.09 |
| CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 0.250000 | $283.06 | $70.77 |
| EQ SANDBLAST 1 | EQUIPO PARA SANDBAST CON ACCESORIOS | HORA | 0.250000 | $16.28 | $4.07 |
| Suma de Equipo | $108.80 | ||||
| Costo Directo | $902.21 |