| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HER-24 | ESCALERA METALICA TUBULAR Y LAMINA ANTIDERRAPANTE EN DESCANSOS DE ANCHO 1.25M CON BARANDAL DE 1.05M DE ALTURA AMBOS LADOS, EL PRECIO UNITARIO INCLUYE: MATERIALES, EQUIPO, MANO DE OBRA Y HERRAMIENTA. (6.00M DE LONG) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO-ESTRUC-002 | VIGA DE ACERO | KG | 256.000000 | $11.50 | $2,944.00 |
| PINTURA-05 | PRIMARIO ANTICORROSIVO | LT | 10.000000 | $49.00 | $490.00 |
| PINTURA-01 | PINTURA DE ESMALTE COMEX 100 | LT | 14.000000 | $60.00 | $840.00 |
| PINTURA-06 | THINNER | LT. | 15.000000 | $16.50 | $247.50 |
| LAMINA ANTIDERR | M2 | 6.000000 | $600.00 | $3,600.00 | |
| SOLDADURA 7018 | SOLDADURA 70/18 | KG | 14.000000 | $22.00 | $308.00 |
| COMBUSTIBLE 06 | GAS P/ CORTES | KG | 10.000000 | $4.05 | $40.50 |
| OXIGENO | OXIGENO | M3 | 6.000000 | $29.00 | $174.00 |
| HERR-07 | PERFIL C-200 CAL 18 | KG | 360.000000 | $16.00 | $5,760.00 |
| ANGULO 1 1/2" X 1/4" | ANGULO 1 1/2" X 1/4" | KG | 86.000000 | $7.12 | $612.32 |
| Suma de Material | $15,016.32 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 22 | (1 OF. Herrero+1 AYUD.) | Jor | 25.000000 | $448.80 | $11,220.00 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 2.000000 | $587.91 | $1,175.82 |
| Suma de Mano de Obra | $12,395.82 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 6.000000 | $0.59 | $3.54 |
| ESMERILADORA | ESMERILADORA | HR | 8.000000 | $19.29 | $154.32 |
| MAQ. SOLDAR EST. | Soldadora Miller Dimension Mod. 652 | HR | 24.000000 | $6.75 | $162.00 |
| Suma de Equipo | $319.86 | ||||
| Costo Directo | $27,732.00 |