Clave | Descripción del Análisis de Precio Unitario | Unidad |
A25025A110 | Tuberia de concreto reposicion de tuberia de concreto (albañal) de 20″de diametro, junteado con mortero de cemento-arenaen proporcion de 1:5. | m |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
BTUCONC051 | Tuberia conc simple c/camp f’c=280kg/cm2 51cm (20″) | M | 1.050000 | $424.16 | $445.37 |
MACMF150 | Polin 3 1/4″x3 1/4″x8 1/4′ | pt | 1.015000 | $6.20 | $6.29 |
BOIAVA025 | Cable manila 1″ 2.5 ml x kg. | kg | 0.109000 | $29.56 | $3.22 |
ACMXX005 | Agua | m3 | 0.089000 | $85.00 | $7.57 |
Suma de Material | $462.45 | ||||
Mano de Obra | |||||
1ATBO | Tubero | Jor | 0.125000 | $379.35 | $47.42 |
1ATBY | Ayudante de tubero | Jor | 0.250000 | $227.31 | $56.83 |
1AABO | Albañil | Jor | 0.075000 | $372.63 | $27.95 |
1AA00 | Peón | Jor | 0.150000 | $227.31 | $34.10 |
1AZC1 | Cabo de oficiales | jor | 0.061000 | $518.10 | $31.60 |
Suma de Mano de Obra | $197.90 | ||||
Herramienta | |||||
2HER | Herramienta menor | (%)mo | 0.000300 | $197.90 | $0.06 |
Suma de Herramienta | $0.06 | ||||
Equipo | |||||
EQHA135-350 | Tripie metálico con garrucha para 2 ton. | hr | 0.666700 | $1.48 | $0.99 |
EQHA135-605 | Grua marca Hiab modelo 035/2 para 510 kg en camion de 3.5 t marca Dodge 3500 6 ton. | hr | 0.233300 | $171.40 | $39.99 |
Suma de Equipo | $40.98 | ||||
Auxiliar | |||||
HA182 | Mortero cemento-arena 1:3 | m3 | 0.023000 | $863.35 | $19.86 |
Suma de Auxiliar | $19.86 | ||||
Costo Directo | $721.25 |