| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 110603 | Caja 40 x 40 en concreto | un |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO60SF01 | Acero refuerzo G-60 sin figurar | kg | 0.600000 | $1,892.00 | $1,135.20 |
| ALAMBRREC18 | Alambre recocido C 18 | kg | 0.010000 | $2,050.00 | $20.50 |
| Suma de Material | $1,155.70 | ||||
| Mano de Obra | |||||
| ZCUADEST | Cuadrilla Estructura | jor | 0.461230 | $115,595.00 | $53,315.88 |
| Suma de Mano de Obra | $53,315.88 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.066000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Concepto | |||||
| 050105 | Formaleta caja 30*30. | un | 1.000000 | $12,434.00 | $12,434.00 |
| 050203 | Concreto 3000 psi en obra | m3 | 0.117000 | $294,870.00 | $34,499.79 |
| Suma de Concepto | $46,933.79 | ||||
| Costo Directo | $101,405.37 |