| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-31 | VIGA DE CONCRETO ARMADO F'c=200 KG/CM2, SECCION 30 x 30 CM, ARMADA CON 8 Vs # 3 Y EST #2 @ 25 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 8.800000 | $16.15 | $142.12 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.200000 | $34.00 | $6.80 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.150000 | $19.00 | $2.85 |
| DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
| CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1" | M | 4.000000 | $2.50 | $10.00 |
| Suma de Material | $167.41 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007500 | $307.31 | $2.30 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.075000 | $251.32 | $18.85 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.075000 | $197.97 | $14.85 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.075000 | $185.16 | $13.89 |
| Suma de Mano de Obra | $49.89 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $49.89 | $1.50 |
| Suma de Herramienta | $1.50 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 3.000000 | $23.47 | $70.41 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 2.000000 | $20.06 | $40.12 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.090000 | $1,322.37 | $119.01 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.090000 | $230.70 | $20.76 |
| Suma de Auxiliar | $250.30 | ||||
| Costo Directo | $469.10 |