Clave | Descripción del Análisis de Precio Unitario | Unidad |
4122-31 | VIGA DE CONCRETO ARMADO F’c=200 KG/CM2, SECCION 30 x 30 CM, ARMADA CON 8 Vs # 3 Y EST #2 @ 25 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 8.800000 | $16.15 | $142.12 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.200000 | $34.00 | $6.80 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.150000 | $19.00 | $2.85 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 4.000000 | $2.50 | $10.00 |
Suma de Material | $167.41 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007500 | $307.31 | $2.30 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.075000 | $251.32 | $18.85 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.075000 | $197.97 | $14.85 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.075000 | $185.16 | $13.89 |
Suma de Mano de Obra | $49.89 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $49.89 | $1.50 |
Suma de Herramienta | $1.50 | ||||
Auxiliar | |||||
ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 3.000000 | $23.47 | $70.41 |
ALAMBRON #2 1 | ALAMBRON DE 1/4″ | KG | 2.000000 | $20.06 | $40.12 |
CONCRETO F-C=200 1 | CONCRETO F’c=200 KG/CM2 | M3 | 0.090000 | $1,322.37 | $119.01 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.090000 | $230.70 | $20.76 |
Suma de Auxiliar | $250.30 | ||||
Costo Directo | $469.10 |