Clave | Descripción del Análisis de Precio Unitario | Unidad |
4080-21 | CIMBRA DE MADERA PARA ACABADO COMUN EN TANQUES ELEVADOS | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 8.400000 | $16.15 | $135.66 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.170000 | $34.00 | $5.78 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
DIESEL 1 | DIESEL | LTO | 0.500000 | $11.28 | $5.64 |
ACERO DE REF 3/8″ 1 | ACERO DE REFUERZO DE 3/8″ | KG | 0.200000 | $14.08 | $2.82 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 0.500000 | $2.50 | $1.25 |
Suma de Material | $153.05 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.011900 | $307.31 | $3.66 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.119050 | $251.32 | $29.92 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.119050 | $197.97 | $23.57 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.059520 | $185.16 | $11.02 |
Suma de Mano de Obra | $68.17 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $68.17 | $2.05 |
Suma de Herramienta | $2.05 | ||||
Equipo | |||||
CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.019050 | $202.91 | $3.87 |
Suma de Equipo | $3.87 | ||||
Costo Directo | $227.14 |