| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2068-59 | SUMINISTRO E INSTALACION DE PTR DE 3 1/2" x 3 1/2" x 1/4" PUNTAL CON PLACAS DE CONTACTO DE 6" x 6" x 3/8"INCLUYE HABILITADO Y MONTAJE | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| PTR 3 1/2X3 1/2X1/4" | PTR ESTRUCTURAL DE 3 1/2" x 3 1/2" x 1/4" | KG | 86.000000 | $18.00 | $1,548.00 |
| PLACA DE ACERO 3/8"1 | PLACA DE ACERO DE 3/8" | KG | 40.000000 | $12.50 | $500.00 |
| ACETILENO 1 | ACETILENO | KG | 1.890000 | $130.00 | $245.70 |
| OXIGENO 1 | OXIGENO | M3 | 2.520000 | $39.00 | $98.28 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 3.150000 | $49.88 | $157.12 |
| Suma de Material | $2,549.10 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.150000 | $307.31 | $46.10 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.500000 | $251.32 | $376.98 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.500000 | $197.97 | $296.96 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.500000 | $185.16 | $277.74 |
| Suma de Mano de Obra | $997.78 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $997.78 | $29.93 |
| Suma de Herramienta | $29.93 | ||||
| Equipo | |||||
| PLANTA SOLDAR 1 | PLANTA DE SOLDAR DE GASOLINA | HORA | 4.000000 | $113.61 | $454.44 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 4.000000 | $26.43 | $105.72 |
| Suma de Equipo | $560.16 | ||||
| Costo Directo | $4,136.97 |