Clave | Descripción del Análisis de Precio Unitario | Unidad |
7108-07 | SUMINISTRO E INSTALACIÓN DE FALSO PLAFON DE 60 x 60 CM INCLUYE ESTRUCTURA SUSPENSION, CORTES, MATERIALES, MANO DE OBRA, EQUIPO Y HERRAMIENTA | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
ALAMBRON DE 1/4″ 1 | ALAMBRON DE 1/4″ | KG | 0.100000 | $16.22 | $1.62 |
TORNILLO 42 MM 1 5/8 | TORNILLO DE 42 MM (1 5/8″) C.D. | PZA | 2.000000 | $0.80 | $1.60 |
ALAMBRE GALV C-14 1 | ALAMBRE GALVANIZADO C-14 | KG. | 0.120000 | $16.00 | $1.92 |
ANGULO PER 3/4″ 1 | ANGULO PERIMETRAL 3/4″ (3.66 ML) | PZA | 0.650000 | $45.00 | $29.25 |
TE PRIN ARMST 1″ 1 | TE PRINCIPAL ARMSTRONG 1″ (3.66 ML) | PZA | 0.900000 | $46.00 | $41.40 |
TE SEC ARMST 1″ 1 | TE SECUNDARIA ARMSTRONG 1″ (0.61 ML) | PZA | 1.750000 | $15.00 | $26.25 |
TE SEC ARMST 1″ 1 | TE SECUNDARIA ARMSTRONG 1″ (0.61 ML) | PZA | 0.900000 | $15.00 | $13.50 |
FALSO PLAF 60*60 CM | FALSO PLAFON DE 60 x 60 CM | M2 | 1.100000 | $44.00 | $48.40 |
Suma de Material | $163.94 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.015000 | $307.31 | $4.61 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.150000 | $251.32 | $37.70 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.150000 | $197.97 | $29.70 |
Suma de Mano de Obra | $72.01 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $72.01 | $2.16 |
Suma de Herramienta | $2.16 | ||||
Costo Directo | $238.11 |