| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AUX-05 | ANDAMIO RENTA POR DIA | DIA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ANDAMIO-03 | MARCO METALIC0 | PZA | 6.000000 | $1.45 | $8.70 |
| ANDAMIO ESCALERA | ESCALERA | pza | 4.000000 | $1.00 | $4.00 |
| ANDAMIO-02 | CRUCETA O TIJERAS AND. ATLAS 255-07 | PZA-- | 8.000000 | $0.48 | $3.84 |
| ANDAMIO-04 | COPLE PARA ANDAMIO | PZA-- | 6.000000 | $0.22 | $1.32 |
| ANDAMIO CRUCETA | CRUCETA PARA ANDAMIO | PZA | 2.000000 | $0.48 | $0.96 |
| ANDAMIO-01 | PLATAFORMA METALICA | PZA | 2.000000 | $4.93 | $9.86 |
| ANDAMIO BARANDAL | BARANDAL | PZA | 1.000000 | $0.43 | $0.43 |
| ANDAMIRUEDAS DE HULE | ruedas de hule | pza | 4.000000 | $1.25 | $5.00 |
| Suma de Material | $34.11 | ||||
| Mano de Obra | |||||
| CUAD OC 02 | CUAD. 1 OP. DE EQUIPO MENOR. | JOR | 0.039302 | $285.51 | $11.22 |
| Suma de Mano de Obra | $11.22 | ||||
| Costo Directo | $45.33 |