| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 11-6190 | ENLADRILLADO DE AZOTEA CON LADRILLO DE BARRO COMUN DE 1.5 X 12.5 X 23.5 CM ACABADO APARENTE ASENTADO CON MORTERO CEMENTO-CALHIDRA-ARENA 1:1:10 INCLUYE ESCOBILLADO CON LECHADA CEMENTO GRIS-AGUA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1850-03 | LADRILLO DE BARRO ROJO RECOCIDO 1.5 X 12.5 X 23.5CM | MIL | 0.035000 | $1,462.43 | $51.19 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.060000 | $18.39 | $1.10 |
| Suma de Material | $52.29 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.095000 | $756.84 | $71.90 |
| Suma de Mano de Obra | $71.90 | ||||
| Auxiliar | |||||
| 03-0330 | MORTERO CEMENTO-CALHIDRA-ARENA 1:1:10 | M3 | 0.025000 | $582.19 | $14.55 |
| Suma de Auxiliar | $14.55 | ||||
| Concepto | |||||
| 03-0670 | LECHADA CEMENTO GRIS-AGUA | M3 | 0.001000 | $2,292.04 | $2.29 |
| Suma de Concepto | $2.29 | ||||
| Costo Directo | $141.03 |