Clave | Descripción del costo horario | Unidad |
EQHA110-100 | Cargador frontal sobre neumáticos mca. Caterpillar mod. 950G motor a Diesel de 180 HP. Cucharón 3.1 m3 al ras peso de operación 17.3 ton. | hr |
DATOS GENERALES | ||||||
Vad = VALOR DE ADQUISICIÓN | $2,160,000.00 | Pnom = POTENCIA NOMINAL | 180.000000 | H.P. | ||
Pn = VALOR DE LAS LLANTAS | $7,320.00 | Fo = FACTOR DE OPERACION | 0 | |||
Pa = VALOR DE PIEZAS ESPECIALES | $0.00 | TIPO DE COMBUSTIBLE | NoUtiliza | |||
Vm = VALOR NETO | $2,152,680.00 | Cco = COEFICIENTE DE COMBUSTIBLE | 0 | |||
Vr = VALOR DE RESCATE | $430,536.00 | Pc = PRECIO DEL COMBUSTIBLE | $5.06 | /LITRO | ||
i = TASA DE INTERES | 7.500000 | /AÑO | ||||
s = PRIMA DE SEGUROS | 2.000000 | /AÑO | ||||
Ko = FACTOR DE MANTENIMIENTO | 0.600000 | HORAS | ||||
Ve = VIDA ECONÓMICA | 16,000.00 | HORAS | ||||
Vn = VIDA ECONÓM. DE LAS LLANTAS | 2,500.00 | HORAS | Gh=CANTIDAD DE COMBUSTIBLE = Cco*Fo*Pnom | 18.630000 | LITROS/HORA | |
Va = VIDA ECONOM. PIEZAS ESPECIALES | 0.00 | HORAS | ||||
Hea = HORAS TRABAJADAS POR AÑO | 1,600.00 | HORAS | ||||
CONCEPTO | OPERACIONES | ACTIVO | EN ESPERA | EN RESERVA | ||
COSTOS FIJOS | ||||||
DEPRECIACIÓN (D) = (Vm-Vr)/Ve | (2152680.00-430536.00)/16000.00 | $107.63 | $16.14 | $16.14 | ||
INVERSIÓN (Im) = [(Vm+Vr)/2Hea]i | [(2152680.00+430536.00)/(2*1600.00)]0.075000 | $60.54 | $60.54 | $60.54 | ||
SEGURO (Sm) = [(Vm+Vr)/2Hea]s | [(2152680.00+430536.00)/(2*1600.00)]0.020000 | $16.15 | $16.15 | $16.15 | ||
MANTENIMIENTO (Mn) = Ko * D | 0.600000*107.63 | $64.58 | $9.69 | $0.00 | ||
Costos fijos | $248.90 | $102.52 | $92.83 | |||
CARGOS POR CONSUMO | ||||||
18.630000*5.06 | $94.27 | $0.00 | $4.71 | |||
OTRAS FUENTES DE ENERGÍA | 0*0 | $0.00 | $0.00 | $0.00 | ||
CAPACIDAD INSTALADA Cpi = Gh/(Hea/Ma)xPc | 18.630000/(1600.000000/0)*5.06 | $0 | $0 | $0 | ||
LLANTAS = Pn/Vn | 7320.00/2500.00 | $2.93 | $0.00 | $0.44 | ||
PIEZAS ESPECIALES = Pa/Va | 0/0 | $0.00 | $0.00 | $0.00 | ||
Cargos por consumo | $106.43 | $0.00 | $5.61 | |||
CARGOS POR OPERACIÓN | ||||||
CATEGORÍA | CANTIDAD | SALARIO REAL | Ht | ACTIVO | EN ESPERA | EN RESERVA |
Operador cargador | 0.125 | $453.20 | 1.000000 | $453.20 | $0.00 | $0.00 |
Cargos por operación | ||||||
Costo Directo por Hora | $411.98 | $102.52 | $98.44 |