| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| DR042-7 | Suministro e instalación de Te PVC cementado19 mm de diametro. Ced. 40 | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0306036 | T HID. CEM. 19 MM | PZ | 1.000000 | $0.80 | $0.80 |
| 9700130 | LIMPIADOR REXOLIT .500 LTS. | PZ | 0.006710 | $9.64 | $0.06 |
| 9700254 | CEMENTO AGRICOLA 480 ML | PZ | 0.012930 | $36.00 | $0.47 |
| Suma de Material | $1.33 | ||||
| Mano de Obra | |||||
| MO04I | Ayudante especializado | jor | 0.001360 | $130.13 | $0.18 |
| Suma de Mano de Obra | $0.18 | ||||
| Herramienta | |||||
| FACHEMEINS | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039INS1 | F-150 PICK-UP XL CAMION SERIE 3FTDF1729XMA29405 | hora | 0.001820 | $110.84 | $0.20 |
| Suma de Equipo | $0.20 | ||||
| Costo Directo | $1.71 |