Clave | Descripción del Análisis de Precio Unitario | Unidad |
CAST0112 | Castillo de 12 x 15 cms de concreto f’c=150 kg/cm2 y armex 12×12-4, incluye: cimbrado, descimbrado, materiales, fabricacion del concreto, colado, mano de obra y herramienta. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01ARM005 | ARMEX 12×12-4 | ML | 1.200000 | $14.51 | $17.41 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.150000 | $18.00 | $2.70 |
06MAD001 | MADERA DE PINO | PT | 1.500000 | $10.00 | $15.00 |
06CLA001 | CLAVOS | KG | 0.160000 | $18.00 | $2.88 |
13DIE000 | DIESEL | LT | 0.240000 | $7.00 | $1.68 |
Suma de Material | $39.67 | ||||
Mano de Obra | |||||
MOF05001 | OFICIAL FIERRERO | JOR | 0.020040 | $401.97 | $8.06 |
MOC05001 | CARPINTERO DE OBRA | JOR | 0.053280 | $401.97 | $21.42 |
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.020160 | $401.97 | $8.10 |
MOA05003 | AYUDANTE | JOR | 0.073320 | $245.43 | $17.99 |
MOA05004 | P E O N | JOR | 0.080640 | $210.17 | $16.95 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $72.52 | $3.63 |
Suma de Mano de Obra | $76.15 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $72.52 | $1.45 |
Suma de Herramienta | $1.45 | ||||
Equipo | |||||
90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.093480 | $10.21 | $0.95 |
Suma de Equipo | $0.95 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.018900 | $1,185.15 | $22.40 |
Suma de Auxiliar | $22.40 | ||||
Costo Directo | $140.62 |