Clave | Descripción del Análisis de Precio Unitario | Unidad |
CIM00070 | Cimbra comun en rampa de escalera, incluye: habilitado, cimbra y descimbra. | LOTE |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
06MAD001 | MADERA DE PINO | PT | 8.000000 | $10.00 | $80.00 |
06CIM005 | CIMBRAPLAY DE 5/8″ | M2 | 1.500000 | $110.00 | $165.00 |
06TUI000 | TUINO DE MADERA | ML | 1.000000 | $4.00 | $4.00 |
06CLA001 | CLAVOS | KG | 2.000000 | $18.00 | $36.00 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.200000 | $18.00 | $3.60 |
13DIE000 | DIESEL | LT | 2.700000 | $7.00 | $18.90 |
Suma de Material | $307.50 | ||||
Mano de Obra | |||||
MOC05001 | CARPINTERO DE OBRA | JOR | 2.000000 | $401.97 | $803.94 |
MOA05003 | AYUDANTE | JOR | 2.000000 | $245.43 | $490.86 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $1,294.80 | $64.74 |
Suma de Mano de Obra | $1,359.54 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $1,294.80 | $25.90 |
Suma de Herramienta | $25.90 | ||||
Costo Directo | $1,692.94 |