| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| TUBER202 | Tuberia galvanizada ced. 40 de 3/4", incluye: suministro y colocacion. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 08TEF000 | TEFLON GARLOCK 3/4" X 10 MTS | PZA | 0.008330 | $28.00 | $0.23 |
| 08TUB202 | TUBO GALVANIZADO CED. 40 DE 3/4" | ML | 1.030000 | $11.36 | $11.70 |
| Suma de Material | $11.93 | ||||
| Mano de Obra | |||||
| MOP05002 | OFICIAL PLOMERO | JOR | 0.016670 | $401.97 | $6.70 |
| MOA05003 | AYUDANTE | JOR | 0.016670 | $245.43 | $4.09 |
| MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $10.79 | $0.54 |
| Suma de Mano de Obra | $11.33 | ||||
| Herramienta | |||||
| HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $10.79 | $0.22 |
| Suma de Herramienta | $0.22 | ||||
| Costo Directo | $23.48 |