| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2.1.3 | ZAPATA DE CIMENTACION AISLADA ( Z3) INCLUYE CIMBRA Y DESCIMBRA DE 200 X 100 CM PERALTE=20 ACERO FY'=4200 KG/CM2 ARMADA CON VARILLA DEL No. 4 @ 20 CMS. EN AMBOS SENTIDOS, GALVANIZADO POR INMERSION EN CALIENTE CONCRETO F´C=250 KG/CM2-3/4" PREMEZCLADO BOMBEADO Y VIBRADO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| GALVANIZADO POR INME | KG | 13.970000 | $3.00 | $41.91 | |
| AGUA | M3 | 0.600000 | $45.00 | $27.00 | |
| Suma de Material | $68.91 | ||||
| Concepto | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 0.400000 | $72.29 | $28.92 |
| CE-03-03 | ACERO DE REFUERZO DEL No. 5 EN CIMENTACION | TON | 0.014000 | $13,029.10 | $182.41 |
| CE-05-02 | F'c= 250 KG/CM2, AGREGADO MAXIMO DE 19 MM., CLASE I | M3 | 0.430000 | $1,181.25 | $507.94 |
| Suma de Concepto | $719.26 | ||||
| Costo Directo | $788.17 |