| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4122-02 | REPIZON DE CONCRETO F'c=200 KG/CM2, SECCION 10 x 20 CM, ARMADO CON 2 Vs # 3 Y EST #2 @ 25 CMS INCLUYE CIMBRA Y DESCIMBRA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 2.000000 | $16.15 | $32.30 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.050000 | $34.00 | $1.70 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.020000 | $19.00 | $0.38 |
| DIESEL 1 | DIESEL | LTO | 0.200000 | $11.28 | $2.26 |
| Suma de Material | $36.64 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003330 | $290.45 | $0.97 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.033330 | $233.90 | $7.80 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.033330 | $181.41 | $6.05 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.033330 | $169.01 | $5.63 |
| Suma de Mano de Obra | $20.44 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 1.200000 | $22.84 | $27.41 |
| ALAMBRON #2 1 | ALAMBRON DE 1/4" | KG | 0.900000 | $19.87 | $17.88 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.020000 | $1,311.84 | $26.24 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.020000 | $215.24 | $4.30 |
| Suma de Auxiliar | $75.83 | ||||
| Costo Directo | $132.91 |