| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| MATERI12 | Materiales de apoyo para reparaciones y mantenimiento del fraccionamiento. | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 02CEM000 | CEMENTO GRIS | KG | 550.000000 | $2.40 | $1,320.00 |
| 01ARM012 | ARMEX 15x20-4 | ML | 8.000000 | $14.00 | $112.00 |
| 19BLO012 | BLOCK DE 12x20x40 CMS CONCRETO TIPO PESADO | PZA | 15.000000 | $7.15 | $107.25 |
| 03ARE000 | ARENA | M3 | 1.500000 | $130.01 | $195.02 |
| 03GRA000 | GRAVA DE 3/4" | M3 | 1.500000 | $130.01 | $195.02 |
| 15PIN120 | PINTURA AMARILLO TRAFICO OSEL ORO | LT | 171.000000 | $78.98 | $13,505.58 |
| 15PIN121 | PINTURA BLANCO TRAFICO OSEL ORO | LT | 38.000000 | $57.13 | $2,170.94 |
| 15PIN122 | PINTURA REDUCTOR XR2 COPE | LT | 38.000000 | $18.14 | $689.32 |
| Suma de Material | $18,295.13 | ||||
| Equipo | |||||
| 90CHRE01 | RETROEXCAVADORA | HR | 4.500000 | $382.95 | $1,723.28 |
| Suma de Equipo | $1,723.28 | ||||
| Costo Directo | $20,018.41 |