| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| *TEMP31 | GUARNICION TIPO TRAPEZOIDAL (SECCION 0.035 M2) A BASE DE CONCRETO PREMEZCLADO F'c=150 Kg/Cm2, VRS 3/8" Ø @ 1,0 MTS, EN ESCUADRA DE 15 x 25 CM DE LARGO, CON 2 VS 3/8"Ø LONGITUDINALES, PASAJUNTAS @ 3.00 M, INCLUYE: CIMBRA, DESCIMBRA, HERRAMIENTA Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| CELOTEX 13MM 1 | CELOTEX 13 MM DE ESPESOR | M2 | 0.180000 | $31.00 | $5.58 |
| CONC PREM 150 1 | CONCRETO PREMEZCLADO F'c=150 KG/CM2 | M3 | 0.036000 | $1,039.28 | $37.41 |
| CURACRETO 1 | CURACRETO | LTO | 0.120000 | $18.00 | $2.16 |
| Suma de Material | $45.15 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.006500 | $307.31 | $2.00 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.065000 | $251.32 | $16.34 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.065000 | $197.97 | $12.87 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.065000 | $185.16 | $12.04 |
| Suma de Mano de Obra | $43.25 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $43.25 | $1.30 |
| Suma de Herramienta | $1.30 | ||||
| Equipo | |||||
| VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE | HORA | 0.200000 | $42.87 | $8.57 |
| Suma de Equipo | $8.57 | ||||
| Auxiliar | |||||
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.250000 | $116.97 | $29.24 |
| Suma de Auxiliar | $29.24 | ||||
| Costo Directo | $127.51 |