Clave | Descripción del Análisis de Precio Unitario | Unidad |
DALA0118 | Dala de cerramiento de 12 x 20 cms de concreto f’c=150 kg/cm2 y armex 12×20-4, incluye: cimbrado, descimbrado, materiales, fabricacion del concreto, colado, mano de obra y herramienta. | ML |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
01ARM006 | ARMEX 12×20-4 | ML | 1.050000 | $13.66 | $14.34 |
01ALA001 | ALAMBRE RECOCIDO No. 16 | KG | 0.150000 | $18.00 | $2.70 |
06MAD001 | MADERA DE PINO | PT | 1.500000 | $10.00 | $15.00 |
13DIE000 | DIESEL | LT | 0.240000 | $7.00 | $1.68 |
06CLA001 | CLAVOS | KG | 0.160000 | $18.00 | $2.88 |
Suma de Material | $36.60 | ||||
Mano de Obra | |||||
MOF05001 | OFICIAL FIERRERO | JOR | 0.020040 | $401.97 | $8.06 |
MOC05001 | CARPINTERO DE OBRA | JOR | 0.060000 | $401.97 | $24.12 |
MOA05001 | OFICIAL ALBAÑIL 1RA. | JOR | 0.022200 | $401.97 | $8.92 |
MOA05003 | AYUDANTE | JOR | 0.080040 | $245.43 | $19.64 |
MOA05004 | P E O N | JOR | 0.088800 | $210.17 | $18.66 |
MI000001 | MANDO INTERMEDIO | (%)MO | 0.050000 | $79.40 | $3.97 |
Suma de Mano de Obra | $83.37 | ||||
Herramienta | |||||
HE000001 | HERRAMIENTA MENOR | (%)MO | 0.020000 | $79.40 | $1.59 |
Suma de Herramienta | $1.59 | ||||
Equipo | |||||
90AND001 | ANDAMIOS METÁLICOS UN MODULO | DIA | 0.102240 | $10.21 | $1.04 |
Suma de Equipo | $1.04 | ||||
Auxiliar | |||||
BASIC005 | CONCRETO F’C=150 KG/CM2, T.M.A. 3/4″ | M3 | 0.025200 | $1,185.15 | $29.87 |
Suma de Auxiliar | $29.87 | ||||
Costo Directo | $152.47 |