| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 9011836 | CODO HIDR CEM 45-100 MM C/L | LOTE |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 0304105 | CODO HID CEM. 45-100 MM | PZ | 1.000000 | $70.06 | $70.06 |
| 9700130 | LIMPIADOR .500 LTS. | PZ | 0.157000 | $17.46 | $2.74 |
| 9700254 | CEMENTO 480 ML | PZ | 0.261000 | $52.91 | $13.81 |
| Suma de Material | $86.61 | ||||
| Mano de Obra | |||||
| 1I1EI | CUADRILLA INSTALACION SISTEMA DE RIEGO 2(1 OF. INST.+1 AY.INST.) | jor | 0.024221 | $782.19 | $18.95 |
| Suma de Mano de Obra | $18.95 | ||||
| Herramienta | |||||
| FACHEME | Herramienta menor | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AMAPE-039 | F-150 PICK-UP XL CAMION MOD 1999 No. Serie 3FTDF1727XMA32545 | hora | 0.004133 | $191.15 | $0.79 |
| Suma de Equipo | $0.79 | ||||
| Costo Directo | $106.35 |