Clave | Descripción del Análisis de Precio Unitario | Unidad |
G300224-1055 | Estructura tipo ts3g para 13 kv para paso de lineas de distribucion | pza |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
300224-1055 | Poste de concreto PCR-12C-750 | pza | 1.000000 | $4,329.15 | $4,329.15 |
300224-5018 | Cruceta C4T | pza | 1.000000 | $576.38 | $576.38 |
175100-1415 | Abrazadera UL | pza | 3.000000 | $69.14 | $207.42 |
300160-2430 | Placa 1PC | pza | 4.000000 | $6.83 | $27.32 |
300224-5036 | Aislador 13 PC | pza | 3.000000 | $507.36 | $1,522.08 |
300160-2100 | Bastidor B1 | pza | 1.000000 | $73.47 | $73.47 |
175100-1015 | Abrazadera 1bs | pza | 1.000000 | $91.01 | $91.01 |
300224-5041 | Carrete H | pza | 1.000000 | $23.01 | $23.01 |
300224-5055 | Bajante de tierra | pza | 1.000000 | $296.01 | $296.01 |
300224-5051 | Conectador | pza | 1.000000 | $68.82 | $68.82 |
Suma de Material | $7,214.67 | ||||
Mano de Obra | |||||
A100110-1025 | Cuadrilla de electricistas en alta tensión. Incluye : Técnico electricista, electricista en alta tensión, ayudante electricista, ayudante general y herramienta. | Jor | 0.650000 | $1,443.14 | $938.04 |
Suma de Mano de Obra | $938.04 | ||||
Costo Directo | $8,152.71 |