| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CIMB APAR MESET | CIMBRA APARENTE PARA MESETAS DE CONCRETO | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1900-05 | MADERA DE PINO DE 3A. EN DUELA DE 1" X 4" | PT | 0.300000 | $12.74 | $3.82 |
| 1900-10 | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 2.950000 | $12.74 | $37.58 |
| 1900-15 | MADERA DE PINO DE 3A. EN POLIN DE 3 1/2" X 3 1/2" | PT | 1.560000 | $6.25 | $9.75 |
| 1900-30 | CHAFLAN DE MADERA DE PINO DE 3A. DE 1" | M | 2.200000 | $4.25 | $9.35 |
| 0100-00 | CLAVO DE 2 1/2" A 3 1/2" | KG | 0.110000 | $18.93 | $2.08 |
| 0082-05 | ALAMBRE RECOCIDO NO. 18 | KG | 0.070000 | $18.00 | $1.26 |
| 0950-05 | DIESEL | LT | 0.500000 | $7.40 | $3.70 |
| 1900-80 | TRIPLAY DE PINO DE 16 MM 1 CARA | HOJA | 0.125000 | $357.58 | $44.70 |
| Suma de Material | $112.24 | ||||
| Mano de Obra | |||||
| CUAD 331- OC | CUADRILLA 331-OC ( OFICIAL CARPINTERO DE OBRA NEGRA+AYUDANTE) | jor | 0.166667 | $784.18 | $130.70 |
| Suma de Mano de Obra | $130.70 | ||||
| Costo Directo | $242.94 |