| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 130513 | Linea primaria aérea 4#2 acsr | ml |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CABLEAC02 | Cable acsr # 2 | ml | 4.000000 | $1,155.00 | $4,620.00 |
| CONECAL | Conectores aluminio | un | 0.150000 | $3,629.00 | $544.35 |
| VARIO | Varios electricos | un | 0.100000 | $1,318.00 | $131.80 |
| Suma de Material | $5,296.15 | ||||
| Mano de Obra | |||||
| ZCUADIEL | Cuadrilla Instalaciones Eléctricas | jor | 0.019796 | $116,803.00 | $2,312.23 |
| Suma de Mano de Obra | $2,312.23 | ||||
| Herramienta | |||||
| HERRA | Herramienta menor | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRMAT | Transporte materiales | glo | 1.000000 | $1,000.00 | $1,000.00 |
| Suma de Auxiliar | $1,000.00 | ||||
| Costo Directo | $8,608.38 |