| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| B-1 | ZAPATA 50X15 CM VS DEL No3 @ 20F`C=200KG | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| 03-2060 | CONCRETO HECHO EN OBRA F'C=200 KG/CM2, RESISTENCIA NORMAL, AGREGADO MAXIMO 3/4" | M3 | 0.093474 | $2,148.60 | $200.84 |
| Suma de Auxiliar | $200.84 | ||||
| Concepto | |||||
| 020201 | CIMBRA Y DESCIMBRA COMUN DE CONTACTO | M2 | 0.315000 | $294.46 | $92.75 |
| 020319 | HABILITADO Y ARMADO DE ACERO DE REFUERZO EN ESTRUCTURA RESISTENCIA NORMAL FY=4200 KG/CM2 No. 3 DIAMETRO 3/8" | TON | 0.008900 | $12,419.50 | $110.53 |
| Suma de Concepto | $203.29 | ||||
| Costo Directo | $404.13 |