| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| AA-001 | SUMINISTRO COLOCACION, JUNTEO Y PRUEBA DE TUBERIA DE ASBESTO CEMENTO CLASE A-5, DE 10" DE DIAM. | ML. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO A.C. A-5 10" | TUBERIA DE ASBESTO CEMENTO CLASE A-5 DE 10" DE DIAM. | ml | 1.050000 | $105.00 | $110.25 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.063700 | $23.00 | $1.47 |
| Suma de Material | $111.72 | ||||
| Mano de Obra | |||||
| MO-027 | TUBERO DE 1ª. | jor | 0.022220 | $330.30 | $7.34 |
| MO-028 | TUBERO DE 2ª. | jor | 0.022220 | $263.56 | $5.86 |
| AYUDANTE | AYUDANTE. | JOR | 0.022220 | $199.89 | $4.44 |
| CABO | CABO DE CUADRILLA | Jor. | 0.003330 | $412.60 | $1.37 |
| Suma de Mano de Obra | $19.01 | ||||
| Herramienta | |||||
| HERRAM | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $130.73 |