| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 06-8010 | ANCLAJE PARA ESTRUCTURA METALICA SOBRE CONCRETO INCLUYE MATERIALES, HABILITADO, MONTAJE Y PINTURA ANTICORROSIVA | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 0128-09 | PLACA DE ACERO DE 3/8" | TON | 0.001100 | $14,993.06 | $16.49 |
| 1551-20 | SOLDADURA E-7018 DE 1/8" | KG | 0.020000 | $59.20 | $1.18 |
| 2600-95 | PINTURA ANTICORROSIVA ( PRIMER ) COMEX | LT | 0.007000 | $43.98 | $0.31 |
| Suma de Material | $17.98 | ||||
| Mano de Obra | |||||
| 02-0780 | CUADRILLA No 78 ( 1 SOLDADOR + 2 AYUDANTES DE SOLDADOR ) | JOR | 0.025000 | $1,066.47 | $26.66 |
| Suma de Mano de Obra | $26.66 | ||||
| Costo Directo | $44.64 |