| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CHAROLA | *CHAROLA DE CONCRETO ARMADO F'C= 200 kg/cm2 con impermeabilizante integral y varilla #4 @15 cm acabado pulido de 0.60 x 0.70 mts. | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERMEABI.INT | IMPERMEABILIZANTE INTEGRAL | M3 | 0.051000 | $70.00 | $3.57 |
| ACE#4 | ACERO DE REFUERZO De 1/2" #4 f`y = 4200 kg/ml | kg | 5.350000 | $6.50 | $34.78 |
| Suma de Material | $38.35 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.250000 | $503.14 | $125.79 |
| Suma de Mano de Obra | $125.79 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 H/O | CONCRETO H.O. F'C=200 KG/CM2, R.N. AGR. MAX. 3/4" | M3 | 0.051000 | $819.38 | $41.79 |
| Suma de Auxiliar | $41.79 | ||||
| Concepto | |||||
| 230.9 | CIMBRA COMUN EN CIMENTACION A BASE DE MADERA DE PINO INCLUYE: CIMBRA, DECIMBRA, ACARREOS, DESMOLDANTE,DESPERDICIOS. | M2 | 0.310000 | $117.70 | $36.49 |
| Suma de Concepto | $36.49 | ||||
| Costo Directo | $242.41 |