| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 540.2 | *GUARNICION TIPO DE PECHO DE PALOMA DE CONCRETO SIMPLE F'C= 200 KG/CM2 10 X 30 X 40 CM.CIMBRA METALICA INCLUYE: TRAZO, CIMBRA, DECIMBRA, MATERIAL, ACARREOS, COLADO, VIBRADO, HERRAMIENTA Y EQUIPO. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| DIESEL | DESMOLDANTE | Lt | 0.500000 | $5.84 | $2.92 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.080000 | $12.00 | $0.96 |
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2AM 3/4" REV. 10 cm +- 2.5 cm | M3 | 0.105000 | $900.00 | $94.50 |
| CELOTEX | junta constructiva a base de celotex | M2 | 0.008330 | $72.56 | $0.60 |
| Suma de Material | $98.98 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.040000 | $503.14 | $20.13 |
| Suma de Mano de Obra | $20.13 | ||||
| Auxiliar | |||||
| BAS -CIMMET | CIMBRA METALICA DE 50 CMS DE ALTURA | ml | 0.020000 | $369.57 | $7.39 |
| Suma de Auxiliar | $7.39 | ||||
| Costo Directo | $126.50 |