| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 15-0210 | LAMBRIN DE DUELA MACHIHEMBRADA DE CAOBA SOBRE BASTIDOR DE MADERA DE PINO DE 1º A CADA 25 CM | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| 1901-95 | DUELA MACHIHEMBRADA DE MADERA DE CAOBA DE 1A. DE 4" | M2 | 1.100000 | $305.62 | $336.18 |
| 1900-40 | MADERA DE PINO DE 1A. | PT | 23.160000 | $39.10 | $905.56 |
| 3250-10 | TAQUETES DE FIBRA Nº 10 X 1" | PZA | 16.000000 | $0.16 | $2.56 |
| 3250-55 | PIJAS Nº 10 X 1" | PZA | 16.000000 | $0.82 | $13.12 |
| 0099-00 | CLAVO DE 1" | KG | 0.080000 | $18.93 | $1.51 |
| 2500-05 | RESISTOL 850 CUBETA DE 19 LITROS | CUB | 0.015000 | $1,158.20 | $17.37 |
| 1902-90 | LIJA PARA MADERA MEDIANA | PZA | 1.000000 | $2.25 | $2.25 |
| Suma de Material | $1,278.55 | ||||
| Mano de Obra | |||||
| 02-0880 | CUADRILLA No 88 ( 1 CARPINTERO DE BANCO + 1 AYUDANTE DE CARPINTERO DE BANCO ) | JOR | 0.266600 | $814.15 | $217.05 |
| Suma de Mano de Obra | $217.05 | ||||
| Costo Directo | $1,495.60 |