| Clave | Descripci贸n del An谩lisis de Precio Unitario | Unidad |
| CIM-12 | Z4 1.00*1.00 DADO DE 0.45*0.45 PARR #4 A/C 13 , 8 #4 EN DADO ESTRIBOS DE #2 A/C 20 DOBLES | PZA |
| Clave | Descripci贸n | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IMPERM. INTEGRAL | IMPERMEABILIZANTE INTEGRAL | M3 | 1.200000 | $80.00 | $96.00 |
| Suma de Material | $96.00 | ||||
| Auxiliar | |||||
| CE-02-01 | CIMBRA COMUN | M2 | 3.400000 | $170.37 | $579.26 |
| CONCRETO BOMB 300 | CONCRETO PREMEZCLADO FC=300 KG/CM2 BOMBEABLE | M3 | 1.200000 | $1,377.66 | $1,653.19 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 109.330000 | $14.89 | $1,627.92 |
| Suma de Auxiliar | $3,860.37 | ||||
| Costo Directo | $3,956.37 |