| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 03-0290 | MORTERO CEMENTO-CALHIDRA-ARENA 1:2:6 | m3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO | CEMENTO NORMAL GRIS TIPO I EN SACO | ton | 0.267000 | $1,896.55 | $506.38 |
| CALIDRA2 | CALHIDRA EN SACO | ton | 0.232900 | $1,300.00 | $302.77 |
| Suma de Material | $809.15 | ||||
| Otros | |||||
| OC-AUX | SUMINISTRO DE MATERIAL DE BANCO (ARENA) PUESTO EN OBRA. INCLUYE MATERIAL Y FLETE. | m3 | 1.122900 | $143.26 | $160.87 |
| OC-AUX3 | AGUA ACARREADA EN PIPA; INCLUYE TRANSPORTE A OBRA Y PAGO DE REGALIAS. | M3 | 0.350000 | $64.90 | $22.72 |
| Suma de Otros | $183.59 | ||||
| Costo Directo | $992.74 |