| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6.07 | RAMPA DE CONCRETO F´C=300 KG/CM2, SUMINISTRADO POR LA PROPIETARIA, EN 12 CM. DE ESPESOR, ARMADO CON VARILLA DEL NUM. 3 A CADA 20 CM. EN AMBOS SENTIDOS, INCLUYE: CIMBRA, ARMADO Y COLADO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MANEJO DE CONCRETO | SUMINISTRADO POR LA PROPIETARIA | M3 | 0.126000 | $167.00 | $21.04 |
| MADERA DE PINO 3A | PT | 1.200000 | $7.50 | $9.00 | |
| CLAVO | CLAVO | KG | 0.100000 | $13.05 | $1.31 |
| AGUA | ACARREO INTERNO | M3 | 0.040000 | $40.00 | $1.60 |
| ACERO REF 3-8 | ACERO DE REFUERZO MCA.T-A | KG | 6.500000 | $9.50 | $61.75 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.200000 | $14.00 | $2.80 |
| DIESEL | DIESEL | LITRO | 0.500000 | $7.00 | $3.50 |
| Suma de Material | $101.00 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | jor | 0.083333 | $697.54 | $58.13 |
| CUADRILLA NO. 16 | (1 Of. Fierrero + 1Ayudante). | JOR | 0.035000 | $667.01 | $23.35 |
| Suma de Mano de Obra | $81.47 | ||||
| Equipo | |||||
| VIBRADOR P/CONCRETO | VIBRADOR PARA CONCRETO MOTOR KOHLE, DE 4 H.P., CON OPERADOR. | HORA | 0.120000 | $52.36 | $6.28 |
| Suma de Equipo | $6.28 | ||||
| Costo Directo | $188.75 |