| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 8, | SUMINISTRO Y COLOCACIÓN DE BLOCK DE CONCRETO CURADO A VAPOR DE 15 X 20 X 40 CMS, RELLENO DE CONCRETO F'C= 200 KG/CM2 Y VR. #3 AHOGADAS AL BLOCK @ 30 CMS. ASENTADO SOBRE ESCALERA DE CONCRETO. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BLOCK 15 X 20 X 40 | BLOCK DE 15 X 20 X 40 | M2 | 12.500000 | $8.00 | $100.00 |
| AGUA | AGUA | M3 | 0.100000 | $80.00 | $8.00 |
| CONCRETO PRE F´C100 | CONCRETO PREMEZCLADO DE F´C=100 KG/CM2 | M3 | 0.040000 | $850.00 | $34.00 |
| Suma de Material | $142.00 | ||||
| Mano de Obra | |||||
| CUA ALBAÑIL 2 | ( 1 ALBAÑIL + 2 PEONES ) | JOR | 0.083333 | $1,499.80 | $124.98 |
| Suma de Mano de Obra | $124.98 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.033600 | $1,246.84 | $41.89 |
| ACERO NO. 3 - 8 | ACERO DE REFUERZO DEL No. 3 AL No.8 | kg | 1.000000 | $18.43 | $18.43 |
| Suma de Auxiliar | $60.32 | ||||
| Costo Directo | $327.31 |