| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 042330 | CHAFLAN DE 10 X 10 CM DE PEDACERIA DE LADRILLO Y MORTERO CEMENTO-ARENA 1:5 | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| 1850-03 | LADRILLO DE BARRO ROJO RECOCIDO 1.5 X 12.5 X 23.5CM | MIL | 0.005000 | $1,200.00 | $6.00 |
| 0302-05 | AGUA DE TOMA MUNICIPAL | M3 | 0.004000 | $3.14 | $0.01 |
| Suma de Material | $6.01 | ||||
| Mano de Obra | |||||
| 02-0410 | CUADRILLA No 41 ( 1 ALBAÑIL + 1 PEON ) | JOR | 0.040000 | $442.94 | $17.72 |
| Suma de Mano de Obra | $17.72 | ||||
| Auxiliar | |||||
| 03-0040 | MORTERO CEMENTO-ARENA 1:5 | M3 | 0.006000 | $607.43 | $3.64 |
| 03-0670 | LECHADA CEMENTO GRIS-AGUA | M3 | 0.000200 | $2,076.37 | $0.42 |
| Suma de Auxiliar | $4.06 | ||||
| Costo Directo | $27.79 |