| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CA03-01 | FABRICACION DE CAJA RECEPTORA DE 1.00 M DE BASE X 2.50 M DE ALTURA CON BLAFE INTERMEDIO EN PLACA DE ACERO DE 3/16", PROTEJIDA CON PINTURA PRIMARIA Y ACABADO CON DOS CAPAS DE PINTURA EPOXICA COLOR BLANCO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PLACA DE ACERO3/16"1 | PLACA DE ACERO DE 3/16" | KG | 37.350000 | $13.50 | $504.23 |
| OXIGENO 1 | OXIGENO | M3 | 1.120500 | $39.00 | $43.70 |
| ACETILENO 1 | ACETILENO | KG | 0.560250 | $130.00 | $72.83 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 1.867500 | $49.88 | $93.15 |
| TORN MAQ ROS 1 | TORNILLO MAQUINA ROSCA STD | KG | 1.867500 | $15.00 | $28.01 |
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 7.470000 | $16.15 | $120.64 |
| PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 0.186750 | $90.00 | $16.81 |
| Suma de Material | $879.37 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.049680 | $290.45 | $14.43 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.497880 | $233.90 | $116.45 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.243760 | $181.41 | $225.63 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.062370 | $169.01 | $10.54 |
| Suma de Mano de Obra | $367.06 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 1.593720 | $111.52 | $177.73 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 1.593720 | $24.34 | $38.79 |
| TALADRO ELECTRICO 1 | TALADRO ELECTRICO BLACK AND DECKER DE PESADO 1/4" | HORA | 1.593720 | $0.95 | $1.51 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.398520 | $200.73 | $79.99 |
| Suma de Equipo | $298.03 | ||||
| Costo Directo | $1,544.46 |