| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| HERRERIA | herreria por kg | kg |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO ESTR | ACERO ESTRUCTURAL, VIGA IPR, PTR,ONTEN, ANGULO, REDONDO Y PLACAS | KG | 1.150000 | $11.40 | $13.11 |
| ESTRU-METALICA-03 | Soldadura e-7018 de 1/8" a 1/4"(3 a 6mm) | Kg | 0.011000 | $40.00 | $0.44 |
| ESTRUC-ALAMBRE | Soldadura de alambre | kg | 0.010000 | $45.00 | $0.45 |
| GAS P/ CORTES | Gas p/corte | KG | 0.009000 | $8.70 | $0.08 |
| COMBUSTIBLE 09 | Oxigeno industrial | m3 | 0.013000 | $60.00 | $0.78 |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $38.00 | $0.08 |
| TORNILLO-1" | tornilleria | kg | 0.003600 | $80.00 | $0.29 |
| RENTA-TALLER | Renta de taller | mes | 0.000100 | $5,000.00 | $0.50 |
| PINTURA Y ACABADO | pintura y acabado | kg | 1.050000 | $3.50 | $3.68 |
| Suma de Material | $19.41 | ||||
| Mano de Obra | |||||
| CUADRILLA JAL-11 | Cuadrilla de oficial soldador y ayudante | JOR | 0.006667 | $750.05 | $5.00 |
| CUADRILLA JAL-10 | Cuadrilla de oficial pailero y ayudante | JOR | 0.008000 | $850.28 | $6.80 |
| Suma de Mano de Obra | $11.80 | ||||
| Equipo | |||||
| A-SOLDADORA | Soldadora Lincon SAE 300 amp. K1277 mot. Perkins 4236, 4 cil, 60 hp, 1600 r.p.m. (sin operador). | HR | 0.021505 | $4.65 | $0.10 |
| A-EQUIPO OXICORTE | Equipo oxi-acetileno para corte (incluye accesorios y consumos) sin operador. | HR | 0.001920 | $168.80 | $0.32 |
| A-GRUA HIDRAULICA | Grua hidraulica 32 ton 152hp todo terreno pluma telescopica 8.8-27.7 m aguilon 7.3/4m peso 21.6 Ton autopropulsada | HR | 0.001000 | $875.39 | $0.88 |
| A TRACTO-CAMION | TRACTO CAMION INTERNATIONAL 9200 MOTOR CUMMINS ISX 450 HP EPA-04 | HR | 0.000126 | $736.00 | $0.10 |
| A-PLATAFORMA BAJA | Plataforma cama baja 13.63 * 3.05 | HR | 0.000500 | $266.47 | $0.13 |
| Suma de Equipo | $1.53 | ||||
| Costo Directo | $32.74 |