| Material | | | | |
| MAC-242 | Cimbra comun de madera de pino de 3a, para castillo | m2 | 0.300000 | $172.08 | $51.62 |
| MAC-033 | Acero de refuerzo numero 5, 5/8" | ton | 0.003000 | $9,975.76 | $29.93 |
| MAC-056 | Alambron trefilado numero 2 | kg | 0.978600 | $13.30 | $13.02 |
| MAC-054 | Alambre recocido calibre 18 | kg | 0.028700 | $14.78 | $0.42 |
| MAC-003 | Agua (toma municipal) | m3 | 0.018500 | $5.20 | $0.10 |
| MAC-242 | Cimbra comun de madera de pino de 3a, para castillo | m2 | 0.300000 | $172.08 | $51.62 |
| MAC-033 | Acero de refuerzo numero 5, 5/8" | ton | 0.003000 | $9,975.76 | $29.93 |
| MAC-056 | Alambron trefilado numero 2 | kg | 0.978600 | $13.30 | $13.02 |
| MAC-054 | Alambre recocido calibre 18 | kg | 0.028700 | $14.78 | $0.42 |
| MAC-003 | Agua (toma municipal) | m3 | 0.018500 | $5.20 | $0.10 |
| Suma de Material | | | | $190.18 |
| Mano de Obra | | | | |
| AUXCDTR-054 | Cuadrilla 54 (oficial albañil y un peon), incluye maestro y mando intermedio | jor | 0.125000 | $1,931.14 | $241.39 |
| AUXCDTR-001 | Cuadrilla 1 (peon), incluye maestro y mando intermedio | jor | 0.013900 | $722.86 | $10.05 |
| AUXCDTR-054 | Cuadrilla 54 (oficial albañil y un peon), incluye maestro y mando intermedio | jor | 0.125000 | $1,931.14 | $241.39 |
| AUXCDTR-001 | Cuadrilla 1 (peon), incluye maestro y mando intermedio | jor | 0.013900 | $722.86 | $10.05 |
| Suma de Mano de Obra | | | | $502.88 |
| Herramienta | | | | |
| HEC-002 | Andamios, pasarelas y escaleras | %mo | 2.000000 | $0.00 | $0.00 |
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| HEC-002 | Andamios, pasarelas y escaleras | %mo | 2.000000 | $0.00 | $0.00 |
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| Suma de Herramienta | | | | $0.00 |
| Equipo | | | | |
| EQC-006 | Vibrador a gasolina, modelo wacker | hr | 0.050000 | $129.41 | $6.47 |
| EQC-006 | Vibrador a gasolina, modelo wacker | hr | 0.050000 | $129.41 | $6.47 |
| Suma de Equipo | | | | $12.94 |
| Auxiliar | | | | |
| AUXCNRN-150 | Concreto f'c= 150 kg/cm2, fabricado en obra, resistencia normal, agregado maximo de 3/4", incluye materiales, desperdicios, mano de obra y equipo | m3 | 0.037800 | $2,096.48 | $79.25 |
| AUXCNRN-150 | Concreto f'c= 150 kg/cm2, fabricado en obra, resistencia normal, agregado maximo de 3/4", incluye materiales, desperdicios, mano de obra y equipo | m3 | 0.037800 | $2,096.48 | $79.25 |
| Suma de Auxiliar | | | | $158.50 |
| Costo Directo | | | | $864.50 |