Clave | Descripción del Análisis de Precio Unitario | Unidad |
E03.021 | Losa de concreto f’c=200 kg/cm2 para obras especiales, incluye: cimbra, acero de refuerzo y chaflanes. | m2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MATE-108 | Clavo de 2 1/2″ a 3 1/2″ | kg | 0.300000 | $18.11 | $5.43 |
MATE-455 | Triplay de pino de 16mm 1 cara (para cimbra) | HOJA | 0.067200 | $390.00 | $26.21 |
MATE-192 | Diesel | l | 0.500000 | $11.07 | $5.54 |
MATE-348 | Poliestireno de 1″ de espesor | m2 | 0.251000 | $13.42 | $3.37 |
MATE-544 | Varilla fy=4200 kg/cm2 No.6 (3/4″) | kg | 20.301000 | $9.50 | $192.86 |
MATE-20 | Alambrón liso de 1/4″ (No.2) | kg | 1.722000 | $11.00 | $18.94 |
MATE-540 | Varilla fy=4200 kg/cm2 No.3 (3/8″) | kg | 4.983000 | $9.50 | $47.34 |
MATE-542 | Varilla fy=4200 kg/cm2 No.4 (1/2″) | kg | 6.198200 | $9.50 | $58.88 |
MATE-543 | Varilla fy=4200 kg/cm2 No.5 (5/8″) | kg | 5.587100 | $9.50 | $53.08 |
MATE-19 | Alambre recocido del No.18 | kg | 1.060000 | $12.50 | $13.25 |
MATE-298 | Madera de pino de 3a. | PT | 4.000000 | $14.39 | $57.56 |
Suma de Material | $482.46 | ||||
Mano de Obra | |||||
00-M0001 | Cuadrila 01 (Ayudante) | jor | 0.390000 | $334.92 | $130.62 |
00-M0006 | Cuadrilla 06 (Carpintero de Obra Negra + Ayudante) | jor | 0.110000 | $805.02 | $88.55 |
00-M0007 | Cuadrilla 07 (Fierrero + Ayudante) | jor | 0.400000 | $794.12 | $317.65 |
Suma de Mano de Obra | $536.82 | ||||
Equipo | |||||
E00.006 | Vibrador para concreto Dynapac-Kohler | h | 0.040000 | $84.77 | $3.39 |
Suma de Equipo | $3.39 | ||||
Auxiliar | |||||
E00.017 | Concreto f’c=200 kg/cm2 | m3 | 0.104000 | $1,145.94 | $119.18 |
Suma de Auxiliar | $119.18 | ||||
Costo Directo | $1,141.85 |