| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| .4 | ACOSTILLADO DE TUBERÍA DE CONCRETO PARA DRENAJE | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 4.560000 | $5.90 | $26.90 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 4.560000 | $5.90 | $26.90 |
| ARENA | ARENA | M3 | 1.300000 | $30.00 | $39.00 |
| ARENA | ARENA | M3 | 1.300000 | $30.00 | $39.00 |
| Suma de Material | $131.81 | ||||
| Mano de Obra | |||||
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.066670 | $576.23 | $38.42 |
| CUADRILLA E-OC-02 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.066670 | $576.23 | $38.42 |
| Suma de Mano de Obra | $76.83 | ||||
| Costo Directo | $208.64 |