| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A25005A095 | Alcantarillas tubulares de concreto tuberia de concreto, p.u.o.t. reforzado de f'c=300 kg/cm2: -colocacion de tuberia de concreto de 150 cm. de diametro | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| BTUCR0208 | Tuberia conc reforzado f'c=300kg/cm2 s.c.t. 150cm (60") | M | 1.010000 | $3,740.00 | $3,777.40 |
| MACMF150 | Polin 3 1/4"x3 1/4"x8 1/4' | pt | 2.080000 | $6.20 | $12.90 |
| BOIAVA025 | Cable manila 1" 2.5 ml x kg. | kg | 0.183000 | $29.56 | $5.41 |
| Suma de Material | $3,795.71 | ||||
| Mano de Obra | |||||
| 1ATBO | Tubero | Jor | 0.145000 | $379.35 | $55.01 |
| 1ATBY | Ayudante de tubero | Jor | 0.575000 | $227.31 | $130.70 |
| 1AABO | Albañil | Jor | 0.145000 | $372.63 | $54.03 |
| 1AA00 | Peón | Jor | 0.287500 | $227.31 | $65.35 |
| 1AZC1 | Cabo de oficiales | jor | 0.115000 | $518.10 | $59.58 |
| Suma de Mano de Obra | $364.67 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $364.67 | $0.11 |
| Suma de Herramienta | $0.11 | ||||
| Equipo | |||||
| EQHA135-350 | Tripie metálico con garrucha para 2 ton. | hr | 1.388800 | $1.48 | $2.06 |
| EQHA135-605 | Grua marca Hiab modelo 035/2 para 510 kg en camion de 3.5 t marca Dodge 3500 6 ton. | hr | 0.468800 | $171.40 | $80.35 |
| EQHA135-600 | Grua marca Hiab modelo 225E-7 para 19.8 Toneladas nominales, montada en camión plataforma mca. International, mod. 4400 de 300 HP. caja útil de 16 T. plataforma de 2.40 x 5.24 m. | hr | 0.681300 | $394.73 | $268.93 |
| Suma de Equipo | $351.34 | ||||
| Auxiliar | |||||
| HA182 | Mortero cemento-arena 1:3 | m3 | 0.038500 | $863.35 | $33.24 |
| Suma de Auxiliar | $33.24 | ||||
| Concepto | |||||
| A05040B005 | Extracción de agua en rio directo a pipa, incluye acarreo en pipa a 10 km. | m3 | 0.176000 | $17.05 | $3.00 |
| Suma de Concepto | $3.00 | ||||
| Costo Directo | $4,548.07 |