| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 4150 | Senales de alineamiento horizontal fantasma de concreto. | pza |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| MAC117 | Pintura vinilica super Kem-tone sherwin >>Blanca mate | l | 0.178600 | $76.41 | $13.65 |
| MAC118 | Pintura vinilica super Kem-tone sherwin >>Negro mate | l | 0.050000 | $76.41 | $3.82 |
| MAC128 | Scotch lite grado ingenieria blanco | m2 | 0.061300 | $177.93 | $10.91 |
| MAC104 | Molde metalico | m2 | 0.408400 | $552.31 | $225.56 |
| Suma de Material | $253.94 | ||||
| Mano de Obra | |||||
| CUC5 | Cuadrilla No. 5: albañil + peón | jor | 0.041700 | $756.96 | $31.57 |
| CUC2 | Cuadrilla No. 2: peón + 1/10 cabo | jor | 0.050000 | $342.67 | $17.13 |
| Suma de Mano de Obra | $48.70 | ||||
| Herramienta | |||||
| HEC1 | Herramienta menor | (%)mo | 0.030000 | $48.70 | $1.46 |
| Suma de Herramienta | $1.46 | ||||
| Auxiliar | |||||
| AUC38 | Acero de refuerzo No. 2 (1/4" diam.) fy=4200kg/cm2; incluye costo de adquisición, carga y descarga + acarreo al 1 er km y acarreo en 49 kms. subsecuentes. | t | 0.000200 | $9,634.37 | $1.93 |
| AUC610 | Acero de refuerzo No. 3 (3/8" diam.) fy= 4200 kg/cm2; incluye costo de adquisicion,carga y descarga + acarreo al1er km, y acarreo en 49kms subsecuentes >>3 varillas*1.8m*0.557kg/m*1.03desp=>>3.098 kg | ton | 0.001600 | $9,625.92 | $15.40 |
| AUC27 | Concreto hidraulico de f'c=100 kg/cm2, rev. max. 14 cms, tma 3/4" hecho en obra agre gados producido por el contratista. | m3 | 0.013700 | $1,297.61 | $17.78 |
| AUC52 | 2) En material "B" | m3 | 0.036000 | $163.53 | $5.89 |
| Suma de Auxiliar | $41.00 | ||||
| Costo Directo | $345.10 |