| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A25025A135 | Tuberia de concreto reforzado de f'c = 280 kg/cm2 de: -152 cm. de diametro. | m |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| TCN04009 | Tubo de 152 cm (60") de diametro,2.50m de largo, (2.44m de largo util) de concreto reforzado Norma S.C.T., Grado S.c.T. Marca Cocomsa. | pza | 1.010000 | $9,350.00 | $9,443.50 |
| MACMF150 | Polin 3 1/4"x3 1/4"x8 1/4' | pt | 3.120000 | $6.20 | $19.34 |
| BOIAVA025 | Cable manila 1" 2.5 ml x kg. | kg | 0.184000 | $29.56 | $5.44 |
| ACMXX005 | Agua | m3 | 0.191000 | $85.00 | $16.24 |
| Suma de Material | $9,484.52 | ||||
| Mano de Obra | |||||
| 1ATP4 | Estadalero | Jor | 0.155000 | $227.31 | $35.23 |
| 1ATBY | Ayudante de tubero | Jor | 0.620000 | $227.31 | $140.93 |
| 1AABO | Albañil | Jor | 0.155000 | $372.63 | $57.76 |
| 1AA00 | Peón | Jor | 0.310000 | $227.31 | $70.47 |
| 1AZC1 | Cabo de oficiales | jor | 0.122000 | $518.10 | $63.21 |
| Suma de Mano de Obra | $367.60 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $367.60 | $0.11 |
| Suma de Herramienta | $0.11 | ||||
| Equipo | |||||
| EQHA135-350 | Tripie metálico con garrucha para 2 ton. | hr | 0.154500 | $1.48 | $0.23 |
| EQHA135-605 | Grua marca Hiab modelo 035/2 para 510 kg en camion de 3.5 t marca Dodge 3500 6 ton. | hr | 0.510000 | $171.40 | $87.41 |
| Suma de Equipo | $87.64 | ||||
| Auxiliar | |||||
| HA182 | Mortero cemento-arena 1:3 | m3 | 0.038300 | $863.35 | $33.07 |
| Suma de Auxiliar | $33.07 | ||||
| Costo Directo | $9,972.94 |