| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A15065A035 | Aplicacion de aditivo adhesivo para concreto a razon de 0.50 lt/m2, p.u.o.t. | m2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
|---|---|---|---|---|---|
| Material | |||||
| AIBFE201 | Epoxine 200 marca Fester | lto | 0.650000 | $533.04 | $346.48 |
| MACMF150 | Polin 3 1/4"x3 1/4"x8 1/4' | pt | 0.208000 | $6.20 | $1.29 |
| ACMXX005 | Agua | m3 | 0.002500 | $85.00 | $0.21 |
| Suma de Material | $347.98 | ||||
| Mano de Obra | |||||
| 1AABO | Albañil | Jor | 0.092500 | $372.63 | $34.47 |
| 1AA00 | Peón | Jor | 0.092500 | $227.31 | $21.03 |
| 1AZC1 | Cabo de oficiales | jor | 0.009300 | $518.10 | $4.82 |
| Suma de Mano de Obra | $60.32 | ||||
| Herramienta | |||||
| 2HER | Herramienta menor | (%)mo | 0.000300 | $60.32 | $0.02 |
| Suma de Herramienta | $0.02 | ||||
| Costo Directo | $408.32 |