Clave | Descripción del Análisis de Precio Unitario | Unidad |
7108-05 | SUMINISTRO Y COLOCACION DE MURO FALSO DE TABLAROCA A DOS CARAS, CON BASTIDOR METALICO, PARA DIVISIONES | M2 |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
POSTE MET YPSA 410 1 | POSTE METALICA YPSA 410 | ML | 2.150000 | $27.00 | $58.05 |
CANAL AMARRE 1 | CANAL DE AMARRE YPSA 410 | ML | 0.950000 | $17.60 | $16.72 |
TABLAROCA 12.7 1 | TABLAROCA SHEETROCK NORMAL 12.7 | M2 | 2.200000 | $41.00 | $90.20 |
COMPUESTO P/JUN 1 | COMPUESTO P/JUNTAS REDIMIX 25 KG | KG | 1.450000 | $8.00 | $11.60 |
TORNILLO HILO 1 | TORNILLO HI*LO YPSA 25.40 MM | MIL | 0.020000 | $88.00 | $1.76 |
TAQUETE PLAS 1 | TAQUETE DE PLASTICO ANCHOR E-2 | PZA | 1.500000 | $3.30 | $4.95 |
REF P/JUN PERFACINTA | REFUERZO PARA JUNTAS PERFACINTA | ROLL | 0.030000 | $29.00 | $0.87 |
Suma de Material | $184.15 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.007000 | $307.31 | $2.15 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.070000 | $251.32 | $17.59 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.070000 | $197.97 | $13.86 |
Suma de Mano de Obra | $33.60 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $33.60 | $1.01 |
Suma de Herramienta | $1.01 | ||||
Costo Directo | $218.76 |