Clave | Descripción del Análisis de Precio Unitario | Unidad |
5082-03 | DISEÑO Y FABRICACION E INSTALACION DE ESTRUCTURA DE BRAZO GIRATORIO INCLUYENDO OBRA CIVIL Y CANASTILLAS NUEVAS PARA RETENCION DE SOLIDOS | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TUBO ACERO 16″ 1 | TUBO DE ACERO CED-80 DE 16″ DE DIAMETRO | M | 10.000000 | $7,700.00 | $77,000.00 |
VIGUETA AC IPS 12″ 1 | VIGUETA DE ACERO IPS DE 12″ | PZA | 1.000000 | $18,500.00 | $18,500.00 |
TROLE CARGA 3000 KG | TROLE DE CARGA DE 3,000 KG | PZA | 1.000000 | $7,350.00 | $7,350.00 |
CARRUCHA 3000 KG | CARRUCHA MANUAL DE 3,000 KG | PZA | 1.000000 | $17,250.00 | $17,250.00 |
SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 2.000000 | $49.88 | $99.76 |
ACETILENO 1 | ACETILENO | KG | 0.250000 | $130.00 | $32.50 |
OXIGENO 1 | OXIGENO | M3 | 0.250000 | $39.00 | $9.75 |
PINTURA ANTICORR 1 | PINTURA ANTICORROSIVA | LTO | 6.000000 | $90.00 | $540.00 |
PINT ESMALTE 1 | PINTURA ESMALTE | LTO | 10.000000 | $90.00 | $900.00 |
THINER 1 | THINER PARA PINTURA EPOXIMASTIC | LTO | 3.000000 | $40.00 | $120.00 |
Suma de Material | $121,802.01 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.800000 | $307.31 | $245.85 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 8.000000 | $251.32 | $2,010.56 |
AYUDANTE OP ESP 1 | AYUDANTE OPERARIO ESPECIALISTA | JOR | 8.000000 | $195.39 | $1,563.12 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 8.000000 | $197.97 | $1,583.76 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 4.000000 | $185.16 | $740.64 |
Suma de Mano de Obra | $6,143.93 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $6,143.93 | $184.32 |
Suma de Herramienta | $184.32 | ||||
Equipo | |||||
SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 20.000000 | $113.61 | $2,272.20 |
COMPRESOR AIRE 250 2 | COMPRESOR DE AIRE INGERSOLL RAND DE 250 PCM MOTOR DIESEL 105 HP | HORA | 4.000000 | $163.21 | $652.84 |
EQ SANDBLAST 1 | EQUIPO PARA SANDBAST CON ACCESORIOS | HORA | 4.000000 | $16.28 | $65.12 |
CAMION WINCHE 1 | CAMION WINCHE FORD DE 5 TON DE CAPACIDAD | HORA | 2.000000 | $285.24 | $570.48 |
Suma de Equipo | $3,560.64 | ||||
Costo Directo | $131,690.90 |