Clave | Descripción del Análisis de Precio Unitario | Unidad |
4122-19 | VIGA EN ALERO DE LOSA DE CONCRETO ARMADO F’c=250 KG/CM2, SECCION 30 x 40 CM, ARMADA CON 6 Vs # 8 Y EST #3 @ 30 CMS INCLUYE CIMBRA Y DESCIMBRA | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 15.600000 | $16.15 | $251.94 |
CLAVO 1/2″ 1 | CLAVO 1/2″ | KG | 0.320000 | $34.00 | $10.88 |
ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.200000 | $19.00 | $3.80 |
DIESEL 1 | DIESEL | LTO | 0.800000 | $11.28 | $9.02 |
CHAF P/MAD 1 | CHAFLAN PARA MADERA DE 1″ | M | 8.000000 | $2.50 | $20.00 |
Suma de Material | $295.64 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.014000 | $307.31 | $4.30 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.140000 | $251.32 | $35.18 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.140000 | $197.97 | $27.72 |
OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.140000 | $185.16 | $25.92 |
Suma de Mano de Obra | $93.12 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $93.12 | $2.79 |
Suma de Herramienta | $2.79 | ||||
Auxiliar | |||||
ACERO REF #6 1 | ACERO DE REFUERZO # 6 | KG | 36.000000 | $17.93 | $645.48 |
ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.400000 | $23.47 | $56.33 |
CONCRETO F-C=250 1 | CONCRETO F’c=250 KG/CM2 | M3 | 0.240000 | $1,417.80 | $340.27 |
VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.240000 | $230.70 | $55.37 |
Suma de Auxiliar | $1,097.45 | ||||
Costo Directo | $1,489.00 |