Clave | Descripción del Análisis de Precio Unitario | Unidad |
1241-05 | INTERCONEXION A 220V AL CENTRO DE CARGA INCLUYE TUBERIA CONDUIT DE PARED GRUESA DE 1″ DE DIAMETRO Y CABLE DE CAL # 10, HERRAMIENTA, EQUIPO, MATERIAL Y MANO DE OBRA NECESARIA | PZA |
Clave | Descripción | Unidad | Cantidad | Costo | Importe |
---|---|---|---|---|---|
Material | |||||
TUBO COND 1″ 1 | TUBO CONDUIT 1″ GALVANIZADO P/GRUESA | M | 35.000000 | $79.20 | $2,772.00 |
TUBO COND 2″ 1 | TUBO CONDUIT 2″ GALVANIZADA P/GRUESA | M | 35.000000 | $212.32 | $7,431.20 |
CAJA CHAL 4″ 1 | CAJA CHALUPA 4″ | PZA | 1.000000 | $8.80 | $8.80 |
CABLE # 8 1 | CABLE THWN CAL # 8 | M | 35.000000 | $16.80 | $588.00 |
CABLE # 10 1 | CABLE THWN CAL # 10 | M | 35.000000 | $8.00 | $280.00 |
Suma de Material | $11,080.00 | ||||
Mano de Obra | |||||
CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.175000 | $307.31 | $53.78 |
OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.750000 | $251.32 | $439.81 |
AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.750000 | $197.97 | $346.45 |
Suma de Mano de Obra | $840.04 | ||||
Herramienta | |||||
HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $840.04 | $25.20 |
Suma de Herramienta | $25.20 | ||||
Costo Directo | $11,945.24 |